CURRENT STATUS: All parties prepare documentation for hearing

See where this fits in the overall plan change process [PDF, 419 KB].

About the private plan change

On 5 October 2021 Two Chain Road Limited lodged a private plan change request with the Council. The request seeks a change to the Operative Selwyn District Plan by rezoning approximately 98 hectares of current rural land in Rolleston to  Business 2A Zone. This would enable an industrial zone.

On this page you can find all the information on the plan change request, including material that has been made available at each stage of the application process.

Map showing the proposed site

Update 16 August 2022

A Commissioner has been appointed and a hearing is to be held at the Lincoln Event Centre, 15 Meijer Drive, Lincoln in the Habgood Lounge from Thursday 20 October 2022 to Friday 21 October 2022, to consider the application.

The Commissioner's Hearing Minute circulated on 16 August 2022 requested that expert evidence be pre-circulated at set times.

The Officer's report is currently being prepared and will be available to view on 28 September 2022.

Update 28 June 2022 - Further Submissions Closed

The period for further submissions closed on 22 June 2022. No further submissions were received.

The next steps will be to determine if any further information is required in response to the matters raised in submissions, and to schedule a hearing.

Update 8 June 2022 - Further Submissions

The original submissions have been summarized and are open for further submissions until 5pm, Wednesday 22 June 2022. The period for further submissions was publicly notified in the Selwyn Times on 8 June 2022.

Public Notice [PDF, 37 KB]

Summary of Submissions
Submitter's Contact Details [PDF, 66 KB]

Further submissions may only be lodged by any person representing a relevant aspect of the public interest or that has an interest in the plan change greater than the interest the public has, or by the local authority itself.

Further submissions must be limited to matters either in support of or in opposition to an original submission made on Plan Change 80. This must be in writing and in accordance with Form 6, which is available below or from any Council Service Centre. Further submissions must be served on Selwyn District Council and a copy must be provided to the person who made the original submission no later than 5 working days after a further submission is provided to Council.

Online Submission Form 6 (Submissions closed)
PDF Submission Form 6 (Submissions closed)

Further submissions may be made through the website (this can include uploading attachments) or you can download and print the PDF further submission form.

Further submissions not lodged through the website can be:

Posted to: Selwyn District Council, PO Box 90, Rolleston 7643
Emailed to: submissions@selwyn.govt.nz
Faxed to 347-2799

Update 30 May 2022 - Late Submission Received

A late submission has been received from KiwiRail Holdings Limited in relation to this plan change request. The submission is available to view online on Summit Up.

Update 25 May 2022 - Late Submission Received

A late submission has been received in relation to this plan change request. This is available to view online on Summit Up.

Update 13 May 2022 - Submissions Received

10 submissions were received in relation to PC80 and can be viewed online at Summit Up.

The summary of submissions, and period for further submissions, will be notified in due course.

Update 10 May 2022 - Submissions Closed


Public submissions on Plan Change request 80 closed at 5pm on Monday 9 May 2022. The submissions will be made publicly available in due course. Once submissions have been summarised, the period for further submissions will be notified.

Update 7 April 2022 - Amended Application

The plan change application has been amended to incorporate the further information requested. The following documents superseded the original documents received.

Private Plan Change Request  including s32 report – Updated in response to RFI
Further Information Request Response
Attachment 1 – Record of Titles
Attachment 2 – ODP – Updated in response to RFI
Appendix A Infrastructure Report – Updated in response to RFI to include Appendix C
Appendix B Integrated Transport Assessment – Updated in response to RFI
Appendix C1 Landscape and Visual Impact Assessment – Updated in response to RFI
Appendix C2 Landscape and Visual Impact Assessment – Graphics
Appendix C3 Two Chain Road – Typical Section – In response to RFI
Appendix D Economic Assessment
Appendix E Versatile Soils
Appendix F1 Preliminary Site Investigation
Appendix F2 Hail Plan – In response to RFI
Appendix G1 Ecological Values
Appendix G2 Ecological Values Update – In response to RFI
Appendix H Geotechnical Assessment
Appendix I Noise Assessment
Appendix J Mahaanui Kurataiao Ltd Consultation – In response to RFI

Update 6 April 2022 - Public Notification

Private Plan Change 80 was accepted for notification at Council’s meeting on 23 March 2022.

The Plan Change was publicly notified in the Selwyn Times newspaper on 6 April 2022.

Public Notice [PDF, 34 KB]

Any person may make a submission in support of or opposition to the plan change, or any part of it. Submissions close at 5pm Monday 9 May 2022.

Online Submission Form 5 (Submissions closed)
PDF Submission Form 5 (Submissions closed)

Submissions may be made through the website or you can download and print the PDF submission form.

Submissions not lodged through the website can be:

Posted to: Selwyn District Council, PO Box 90, Rolleston 7643
Emailed to: submissions@selwyn.govt.nz
Faxed to 347-2799

After 9 May 2022, submissions will be summarised and made available to the public.

Update 14 February 2022

In response to Council’s request dated 9 November 2021, the following response was received on 11 February 2022. The response is currently being reviewed to ensure that the matters raised in the request for further information have been satisfactorily addressed.

Further Information Request Response [PDF, 661 KB]
Attachment A - HAIL Plan  [PDF, 6055 KB]
Attachment B - Updated s32 Report [PDF, 663 KB]
Attachment C - Updated Section [PDF, 100 KB]
Attachment C - Updated Landscape Assessment [PDF, 298 KB]
Attachment C - Updated ODP [PDF, 225 KB]
Attachment D - Updated ITA [PDF, 2618 KB]
Attachment E - Ecology Update [PDF, 1677 KB]
Attachment F - Appendix 5 Mahaanui Kurataiao Ltd Consultation [PDF, 303 KB]
Attachment G - Updated Appendix C of Infrastructure Report [PDF, 3448 KB]

Update 17 November 2021 

The application has been reviewed and a request for further information was issued on 9 November 2021.

Further Information Requested [PDF, 879 KB]

Update 5 October 2021 - Private plan change application received

The request is currently being reviewed to ensure the information is adequate for public notification. Once this has been completed and any required information received it will be taken to Council to be considered for notification. If Council decides to accept the request it will be publicly notified and opened to submissions.

Application:

The Plan Change request consists of the following documents:
Due to the size of the Application, it has been broken into component parts:

Private plan change request - Two Chain Road Limited and Attachment 3 s32 report [PDF, 657 KB]
Attachment 1 Record of Titles [PDF, 1000 KB]
Attachment 2 Outline Development Plan [PDF, 240 KB]
Appendix A Infrastructure Report [PDF, 6077 KB]
Appendix B Integrated Transport Assessment [PDF, 2157 KB]
Appendix C Landscape and Visual Impact Assessment [PDF, 260 KB]
Appendix C Landscape and Visual Impact Assessment - Graphics [PDF, 5342 KB]
Appendix D Economic Assessment [PDF, 243 KB]
Appendix E Versatile Soils [PDF, 885 KB]
Appendix F Preliminary Site Investigation [PDF, 15546 KB]
Appendix G Ecological Values [PDF, 1284 KB]
Appendix H Geotechnical Assessment [PDF, 6974 KB]
Appendix I Noise Assessment [PDF, 739 KB]

Contact

For further information contact the team on 0800 SELWYN (735 996) or email contactus@selwyn.govt.nz