The Lincoln Town Centre Upgrade will be delivered in four stages to support Lincoln’s growth and ensure works are carried out safely and efficiently.
Stage One focuses on upgrading Gerald Street between Kildare Terrace and West Belt, marking an important first step in future‑proofing the town centre.
Stages Two and Three will build on this work, with road widening and the addition of cycle lanes along Gerald Street from West Belt to Springs Road.
Stage Four will complete upgrades to Gerald Street between Kildare Terrace and the James Street / Edward Street intersection.
The project is underway and progressing as planned. Details about later stages will be shared as work advances, with regular updates provided so the community knows what’s happening and when.
Stage One
The Stage One upgrade is under way. Stage One is focused on new carparks, slow speed zones, addition of cycle lanes, new Gerald Street plaza, and multiple pedestrian crossings.
You can find more information on Stage One here.
To stay in the Lincoln Loop click here.
Stages Two and Three
Stages Two and Three will focus on renewing the road, the provision of cycle lanes and adding traffic lights at the intersections of Springs Road and Vernon Drive.
Stage Four
Stage Four will involve upgrades to Gerald Street, from Kildare Terrace to James Street, including adding traffic lights to the Gerald, James, and Edward streets intersection.
Stages Two to Four will be completed by 2030.
Stay in the Lincoln loop
Sign for to our newsletter below.
Social media: facebook.com/SelwynDistrictCouncil
Email: lincolntcplan@selwyn.govt.nz
Call: 0800 SELWYN (735 996)
Drop-in sessions: The Fulton Hogan team hold drop-in sessions between 11am and 2pm on a Tuesday or Thursday, at 6/14 Gerald Street (next door to Property Brokers).