Building a safer, more connected town centre

Lincoln is growing, and our town centre needs to grow with it.

Stages 2 and 3 of the Lincoln Town Centre upgrade will deliver major improvements along Gerald Street, helping create a safer, more efficient and more accessible transport corridor for everyone who lives, works and visits Lincoln. These upgrades will support our growing community while improving how people drive, walk, cycle or bus through the town.

The project includes new traffic lights, upgraded underground infrastructure, improved walking and cycling connections, new bus facilities and a full road rebuild. Together, these improvements will help ensure Lincoln's town centre continues to meet the needs of the community for many years to come.

Map showing works around Lincoln as part of stages two and three

Why are these improvements needed?

Lincoln is one of New Zealand's fastest-growing communities, and the transport network needs to keep pace with increasing demand.
These upgrades will:

  • Improve safety at key intersections.
  • Help traffic move more efficiently, with traffic lights that work together.
  • Provide safer routes for walkers and cyclists.
  • New bus shelters.
  • Upgrade ageing underground infrastructure.
  • Support planned growth across the wider Lincoln area.
  • Help create a more resilient and future-ready town centre.

What's happening?

Stages 2 and 3 cover almost 1km of Gerald Street between South Belt and Springs Road, making this a significantly larger and more complex project than Stage 1.

Key improvements include:

  • Traffic lights will be installed at the intersection of Gerald Street, Springs Road and Ellesmere Junction.
  • Traffic lights will also be installed at the intersection of Gerald Street and Vernon Drive.
  • The road will be rebuilt and resurfaced.
  • New water supply pipes will be installed.
  • New stormwater infrastructure will be added to help manage rainwater.
  • Overhead power lines will be moved underground.
  • New street lighting will be installed.
  • New walking and cycling paths will be built on both sides of the road.
  • New bus stops and shelters will be added.
  • The existing open drain on the north side of Gerald Street will be piped underground.

Project Timeline

The project is expected to take about 18 months from the start of construction through to final surfacing, road markings and commissioning the new traffic lights.

Dates are approximate. Highlighted months indicate when each stage is completed or expected, to be completed.

🚧
October 2026

Construction Start

⬆️
March 2027

Pipe Northern Drain

🚶
May 2027

Northern Footpath & Cycleway

⚡
July 2027

Underground Powerlines

💡
July 2027

Streetlights

💧
August 2027

Water Supply

🚲
October 2027

Southern Footpath & Cycleway

🛣️
February 2028

Road Pavement

🎨
February 2028

Line Marking

🚦
March 2028

Traffic Signals Commissioning

✅
April 2028

Construction Finish


Planned construction sequence


Keeping Lincoln moving during construction

We know construction can be disruptive and we are working hard to minimise impacts wherever possible.

Lessons learned from Stage 1 have helped shape the approach for Stages 2 and 3. Work will be carefully staged to maintain access while allowing construction to progress safely and efficiently. Where practical, multiple work areas will operate at the same time to reduce the overall construction programme. Specialist construction methods, including directional drilling, will be used to reduce excavation and disruption.

Map of works for stages 2 and 3. Click the image to zoom in.