low angle image of the Whitecliffs Bridge

We’re replacing the Whitecliffs Bridge

Whitecliffs Road is getting a new bridge. The existing one has linked the community for many decades. It was built in 1935, with major updates in 1959 and 1996, but the time has come for the bridge to be replaced. It is not practical to keep repairing it.

Whitecliffs Road will be closed at the bridge for about six months from late February 2027, and a detour will be in place. The new bridge is planned to open in August 2027. These dates depend on the weather, and we’ll tell people if they change.

The detour is about 5km along Riversleigh Road and includes a ford that heavy rain can make impassable. We’re looking at what we can do to keep the ford open more often. Please allow extra travel time.

Keeping the existing bridge going would cost more than it is worth, and repairs would not give the bridge the width, barriers or footpath it needs for the traffic that uses it today. Inspections found decayed timber piers, cracks in the deck and rusting steel beams. The bridge can carry only 50 percent of normal heavy vehicle loads, which affects school buses, rubbish trucks, emergency services and local industry.

Features of the new bridge:

  • A 100-year design life, with much lower maintenance needs.
  • A concrete deck about 44m long on the existing line, with no joints to wear out.
  • A single traffic lane with modern safety barriers.
  • Replaces the current pinch point  and restores full heavy vehicle access.
  • Supports school buses, rubbish and recycling trucks, emergency services and forestry operations.
  • A separate footpath for safe pedestrian access.
  • Pedestrians can cross without sharing the road with vehicles.
  • A design that meets current NZ Transport Agency standards for floods and earthquakes [TO CONFIRM with Beca].

Timeline

2025 – December

  • Beca carried out ground, river and wildlife assessments to inform an initial design and consent requirements.

2026 – [month TO CONFIRM]

  • Contract awarded to Concrete Structures (NZ) Limited. Detailed design under way.

2026 – late November to 2027 – February

  • Surveys of birds, fish and lizards, finding underground services, vegetation clearance in marked areas and site set-up. Parts of the road shoulder close at times.

2027 – late February

  • Road closes at the bridge. Old bridge taken down. Timber from the old pier frames goes to a Council storage yard.

2027 – March to June

  • New piles, abutments and piers, then bridge beams lifted into place.

2027 – July to August

  • Deck, safety barriers and approach roads. Road reopens in August 2027.

2027 – late August to September

  • Site cleared and native plants go in. Final road sealing planned for spring 2027.

All dates are weather permitting and based on the contractor’s current programme.