Map of Waimak Gorge Bridge

Works Timeline and Traffic Impacts

From Monday 25 March, work will begin on installing scaffolding ahead of replacing the bridge deck. Temporary traffic lights will be in place during this time, please expect delays of up to 10 minutes.

From Tuesday 2 April, for approximately 6 weeks, the deck replacement will commence. Guard rail protection will also be installed as part of this work.

Bridge Closure Nightly from Tuesday 2 April between 7.30pm-4.30am for Approximately 6 Weeks

Works will be undertaken during both the day and night, with the bridge closed nightly from Tuesday 2 April between 7.30pm and 4.30am. Please note - work will not take place on Friday and Saturday nights.

During the day, the bridge will be open to normal traffic flow, with temporary traffic lights in place. Please expect delays of up to 10 minutes.

Detours

During the night time closures, the alternative route is via the SH1 Waimakariri River Bridge near Kaiapoi, this route is approximately 115km in distance so please plan your trip accordingly. Electronic signs will be in place reminding drivers of the closure and to use the alternate route during the closures.

Waimak Gorge Bride Detour

Please take care around the work site and if you would like any further information about this project please contact transportation@selwyn.govt.nz

We thank you for your patience as we undertake this essential work. We will continue to keep you updated on progress and traffic management throughout the works. Please continue to check our Facebook channel and our project page regularly at selwyn.govt.nz/waimakgorgebridge

Last modified: 29 Apr 2024 3:35pm